top of page

City Projects

Long Beach Inner Bulkhead

Ongoing
harbor picture 2 (1).jpg
Click HERE to view plans. 

Long Beach Gateway Project

Ongoing
Screenshot (132).png
Click HERE to view the Environmental Review
Click HERE to view the Environmental Assestment
Click HERE to view plans 

Railroad Crossing Grade Improvement Project

Completed: 2025
railroad crossing project (1).jpg

Asphalt Overlays and Repairs

Completed: 2025
Screenshot (120).png

Park Improvements

Completed: 2025
parks and rec 2.jpg

Trautman Basin Wastewater Improvements

Completed: May 2024

Sewer Rehabilitation

Completed: April 2024
sewer rehab 1 (1).png

Pineville Road Widening

Completed: 2024
0CF7A024-6A50-4328-B465-BCC308EA392D_L0_001-9_30_2024, 2_22_53 PM.jpg
This project included widening and paviang of Pineville Road.
Completed : January 2024

Fire Station NO. 3

fire station 3.jpg
This project included the construction of fire station no. 3 on Johnson Road.

Greenvale

Completed : January 2024
quarles house updated.jpg
This project included extensive renovations and improvements to the Quarles House on East Old Pass Road. The historic building has been restored to its original appearance as the Quarles family residence. 

North Jeff Davis Avenue Extension

Completed : January 2024
E969D474-50BA-49F6-98AE-F68C6B6859D9_L0_001-9_30_2024, 2_22_20 PM.jpg
North Jeff Davis Avenue was extended to connect West Railroad Street and East Old Pass Road. This included stormwater infrastructure, utility relocation, and other miscellaneous roadway improvements and restoration.

Signage Project

Completed : 2023
image.png
image.png
Included the addition of two Long Beach Harbor welcome signs and four City of Long Beach pillars. 

Mitchell Road Widening - Phase 1 & Phase 2

Completed : 2023
image.png
image.png
Phase 1 of the Mitchell Road Widening included construction of drainage improvements to allow a future phase 2 of widening South Mitchell Road.

HCUA Wastewater Treatment Improvements - Phase 1 and Phase 2

Completed : 2023
image.png
HCUA wastewater treatment improvements included the removal of all failing Price Bros. pipe from active service, installation of new PVC sewage force mains from North Nicholson Avenue Pump Station to the wastewater treatment plant in Pass Christian, and several miscellaneous improvements at several pump stations serving the city.

Lynnwood Cricle Water Improvements

Completed : 2023
image.png
image.png
Lynnwood Circle water system improvements included the replacement of small diameter and failing water main infrastructure, fire hydrants to improve fire fighting capabilities, and included an asphalt overlay of the subdivision.

Long Beach Senior Center Generator

Completed : April 2023
image.png
A generator was installed to service the Long Beach Senior Center during power outages. 

City Hall HVAC Repairs

Completed : February 2023
image.png
Repairs included the removal and replacement of aging HVAC systems at Long Beach City Hall.

Long Beach Public Library Roofing Improvements

Completed : January 2023
Library b4.png
Library after.png
Roofing improvements included the construction and installation of a tapered insulation roof system at the library.

Harbormaster Building Repairs 

Completed : April 2023
image.png
The repairs to the Harbor Master Building included fixing all damages caused by Hurricane Zeta, and included improvements to the function and serviceability of the building for continued service.

2nd Street Sidewalk Extension

Completed : 2023
image.png
This project included the construction of a sidewalk along 2nd street between South Burke Avenue and the USM "Gulf Park" campus, and also included miscellaneous drainage imorovements and restoration.

Trautman Basin Wastewater Improvements

Completed : 2023
image.png
image.png
The Trautman Basin Wastewater improvements included the replacement of the lift station at the Pineville Road and Railroad Street intersection as well as the construction of a new sewage force main along East Railroad Street to improve sewage performance and capacity.

Safe Haven Baby Box

Completed : 2023
image.png
This project included the installation of a Safe Haven Baby Box Drop Off located at Central Fire Station on Klondyke Road.
FIND US
Long Beach MS, City Hall

201 Jeff Davis Ave

Long Beach, MS 39560

​

228.863.1556

 

​

new city logo (4).png
bottom of page